How much does a landscaping & hardscape cost?
For a typical 600 sq ft of project area project at a mid finish level in the Jackson, Ohio area, the estimated range is $9,240 – $16,250.
Estimated range — not a quote. Your contractor's bid is the real number.
What to know before you budget
Landscaping and hardscape are priced together but behave differently: planting is materials plus the labor of putting living things in the ground well, while patios and walkways are construction — excavation, a compacted base, and stone set to shed water for decades. For a typical project covering 600 sq ft of project area around Jackson, Ohio, the $9,240 – $16,250 range above covers a mid-level job. The balance between planting and pavement, and what the site demands underground, decide where you land inside it.
The price drivers, in plain words
The planting-to-pavement mix is the biggest lever
Beds, plants, sod, and mulch price at one level per square foot; patios and walkways price at a clearly higher one, because every paved foot carries excavation, base stone, bedding, the pavers themselves, and edging. A project that is mostly planting with a small patio and one that is mostly patio with planting at the edges are different budgets sharing a name. When you compare bids, compare the mix first — it explains more of the difference than any plant list does.
Paver and stone choices multiply quietly
Concrete pavers are the manufactured standard: uniform, durable, and the economical end of hardscape. Natural stone costs more for the material and more again in labor, because irregular pieces are fitted one at a time. Pattern matters the same way — a simple running bond lays fast, while borders, inlays, and tight curves are handwork. The details underneath count too: proper edge restraints and joint sand are what keep a patio's pattern from wandering over the years.
Irrigation: none, drip, or a full system
New planting without irrigation is a commitment to hand-watering through the first dry summer. Drip lines serve beds efficiently — tubing, emitters, and a timer at modest scope. A full sprinkler system is underground construction: trenched lines, heads by zone, a controller, and a backflow preventer, with the trenching far easier during the project than after it. Each step is a genuine system, not a setting, and the bid should name which one — if any — is in the price.
Grading and drainage are the invisible foundation
A flat, well-drained site lets the visible work start immediately. A site that holds water, slopes toward the house, or needs its shape changed asks for grading first — moving soil, establishing falls, sometimes buried drainage lines or a small retaining edge to hold a new level. It is the least photogenic part of the budget and the part everything else depends on: patios heave and beds drown on sites whose water was never given a plan.
What to ask before you sign
- Ask what base the patio or walkway sits on — the depth of compacted stone and the bedding layer. A patio is only as flat in five years as its base is today.
- Ask where surface water goes after the project. New pavement changes drainage, and the answer should never be “toward the house.”
- Ask what plant sizes the price assumes — container sizes for shrubs, caliper for trees. The same plant list prices very differently in young stock and in mature specimens.
- Ask what is warranted: plants through their first season, hardscape against settling for a stated period — and what the warranty leaves out.
How this range was built
This range comes from our own cost library: labor priced from federal Bureau of Labor Statistics pay data for landscaping and groundskeeping workers and equipment operators, loaded with a standard employer burden, and materials from published cost benchmarks — then adjusted to the Jackson, Ohio area. A bid can land outside it when natural stone replaces pavers, a full sprinkler system joins the scope, or the site needs real grading and drainage first. Treat the range as a planning tool, not a ceiling.
What drives the price
- Planting vs. hardscape mix
- Paver and stone choices
- Irrigation — none, drip, or full sprinklers
- Grading and drainage the site needs
Materials (typical project — ranges)
| Material | Quantity | Subtotal range |
|---|---|---|
| Plants, sod & mulch | 660 sq ft | $2,672 – $3,400 |
| Pavers & hardscape stone | 660 sq ft | $3,099 – $3,944 |
| Base & bedding materials | 660 sq ft | $748 – $952 |
| Irrigation & drainage | 1 systems | $891 – $1,133 |
| Edging & landscape fabric | 660 sq ft | $374 – $476 |
Materials takeoff — what to order (typical project)
| Item | What's in it | Net quantity | Waste allowance | Order quantity |
|---|---|---|---|---|
| Plants, sod & mulch | 600 sq ft | 10% (General materials) | 660 sq ft | |
| Pavers & hardscape stone | 600 sq ft | 10% (General materials) | 660 sq ft | |
| Base & bedding materials | 600 sq ft | 10% (General materials) | 660 sq ft | |
| Irrigation & drainage | 1 systems | 10% (General materials) | 2 systems | |
| Edging & landscape fabric | 600 sq ft | 10% (General materials) | 660 sq ft |
Planning list only — it never changes the estimate price. Net is the quantity the job consumes; Order adds the waste allowance for the material class (the estimate breakdown quantities already include a flat 10% waste factor — this list re-derives net vs order by class, so nothing is counted twice). Counts (studs, sheets, bundles, rolls) use the standard planning conversions stated on each line; confirm counts against the actual plans before ordering.
Labor by trade (ranges & stated assumptions)
| Trade | Hours & crew | Local labor cost range | Subtotal range |
|---|---|---|---|
| Landscaping & planting | 54 hrs · crew of 3 (assumption) | $22.51–$29.06/hr | $1,216 – $1,569 |
| Hardscape installation | 66 hrs · crew of 3 (assumption) | $22.51–$29.06/hr | $1,486 – $1,918 |
| Grading & prep | 18 hrs · crew of 2 (assumption) | $29.27–$47.37/hr | $527 – $853 |
Trades this project needs, in order
- Landscaping & planting
- Hardscape installation
- Grading & prep
Your first estimate is free. Want it as a document you can plan and compare bids with? The Project Plan ($49 one-time) — scope breakdown, budget worksheet, bid-comparison kit, and red-flag guide, built from your project's numbers — is offered the moment your estimate is ready.
Related cost guides
- Fencing cost guide
- Concrete driveway / patio cost guide
- Inground pool build cost guide
- Already have a bid? Check it free
ProjectBridge cost library (costlib v0.2) — our own cost database, built from public data (federal labor statistics and published cost benchmarks) and local price checks. Ranges only; not a quote.