How much does a concrete driveway / patio cost?
For a typical 600 sq ft project at a mid finish level in the Jackson, Ohio area, the estimated range is $4,582 – $8,058.
Estimated range — not a quote. Your contractor's bid is the real number.
What drives the price
- Thickness (4 in. vs. 6 in.) and reinforcement
- Tear-out of the old surface
- Finish: broom vs. stamped vs. exposed aggregate
- Site access for the mixer truck
- Drainage corrections
Materials (typical project — ranges)
| Material | Quantity | Subtotal range |
|---|---|---|
| Ready-mix concrete (4 in.) | 8.58 cubic yards | $1,077 – $1,370 |
| Concrete delivery & short-load fees | 1 loads | $182 – $232 |
| Gravel base | 660 sq ft | $561 – $714 |
| Rebar / wire mesh | 660 sq ft | $454 – $578 |
| Forms & stakes | 660 sq ft | $427 – $544 |
| Sealer & finish materials | 660 sq ft | $427 – $544 |
Labor by trade (ranges & stated assumptions)
| Trade | Hours & crew | Local labor cost range | Subtotal range |
|---|---|---|---|
| Excavation & grading | 12 hrs · crew of 2 (assumption) | $34.67–$59.19/hr | $416 – $710 |
| Form, pour & finish | 34.8 hrs · crew of 3 (assumption) | $31.32–$48.83/hr | $1,090 – $1,699 |
| Old surface tear-out & haul-off | 12 hrs · crew of 2 (assumption) | $29.27–$47.37/hr | $351 – $568 |
Trades this project needs, in order
- Excavation & grading
- Form, pour & finish
- Old surface tear-out & haul-off