How much does a whole-home remodel cost?
For a typical 1500 sq ft remodeled project at a mid finish level in the Jackson, Ohio area, the estimated range is $147,645 – $259,651.
Estimated range — not a quote. Your contractor's bid is the real number.
What drives the price
- How much layout changes — moving walls, plumbing, or electrical
- Kitchen and bathroom scope inside the remodel
- Structural, rot, or water damage found after demo
- Systems at end of life (panel, repipe, HVAC) replaced while walls are open
- Finish level across the whole home, not just one room
Materials (typical project — ranges)
| Material | Quantity | Subtotal range |
|---|---|---|
| Framing & structural materials | 1650 sq ft | $13,358 – $17,002 |
| Insulation & drywall | 1650 sq ft | $13,358 – $17,002 |
| Flooring throughout | 1650 sq ft | $14,694 – $18,702 |
| Kitchen package allowance | 1 packages | $12,954 – $16,486 |
| Bathroom package allowance | 1 packages | $8,906 – $11,334 |
| Electrical & plumbing materials | 1650 sq ft | $20,038 – $25,502 |
| Paint, trim & doors | 1650 sq ft | $9,351 – $11,901 |
| Windows & exterior allowance | 1650 sq ft | $12,023 – $15,301 |
Labor by trade (ranges & stated assumptions)
| Trade | Hours & crew | Local labor cost range | Subtotal range |
|---|---|---|---|
| Demo & disposal | 330 hrs · crew of 3 (assumption) | $29.27–$47.37/hr | $9,658 – $15,632 |
| Framing & carpentry | 570 hrs · crew of 3 (assumption) | $31.02–$48.32/hr | $17,683 – $27,541 |
| Electrical | 210 hrs · crew of 1 (assumption) | $31.92–$51.27/hr | $6,704 – $10,767 |
| Plumbing | 195 hrs · crew of 1 (assumption) | $31.88–$53.66/hr | $6,216 – $10,464 |
| HVAC work | 75 hrs · crew of 2 (assumption) | $30.83–$49.8/hr | $2,312 – $3,735 |
| Insulation | 75 hrs · crew of 2 (assumption) | $29.11–$50.67/hr | $2,183 – $3,801 |
| Drywall hang & finish | 240 hrs · crew of 2 (assumption) | $31.34–$45.19/hr | $7,520 – $10,846 |
| Tile work | 90 hrs · crew of 1 (assumption) | $26.53–$37.3/hr | $2,388 – $3,357 |
| Flooring install | 165 hrs · crew of 2 (assumption) | $31.53–$46.4/hr | $5,202 – $7,655 |
| Paint & finish | 195 hrs · crew of 2 (assumption) | $28.04–$39.36/hr | $5,468 – $7,675 |
Trades this project needs, in order
- Demo & disposal
- Framing & carpentry
- Electrical — licensed pro
- Plumbing — licensed pro
- HVAC work — licensed pro
- Insulation
- Drywall hang & finish
- Tile work
- Flooring install
- Paint & finish