How much does a room addition cost?
For a typical 400 sq ft added project at a mid finish level in the Jackson, Ohio area, the estimated range is $53,534 – $94,146.
Estimated range — not a quote. Your contractor's bid is the real number.
What drives the price
- Foundation type and site grade
- How the roof ties into the existing house
- Bathroom/kitchen inside the addition
- Matching existing siding and finishes
- Permit, survey and setback requirements
Materials (typical project — ranges)
| Material | Quantity | Subtotal range |
|---|---|---|
| Foundation concrete & block | 440 sq ft | $5,700 – $7,254 |
| Framing package | 440 sq ft | $8,549 – $10,881 |
| Roofing tie-in package | 440 sq ft | $4,275 – $5,441 |
| Siding & exterior trim | 440 sq ft | $4,631 – $5,894 |
| Windows & exterior door | 8 openings | $7,124 – $9,068 |
| Insulation & drywall | 440 sq ft | $3,562 – $4,534 |
| Electrical & HVAC extension materials | 440 sq ft | $4,631 – $5,894 |
| Flooring & interior trim | 440 sq ft | $4,631 – $5,894 |
Labor by trade (ranges & stated assumptions)
| Trade | Hours & crew | Local labor cost range | Subtotal range |
|---|---|---|---|
| Excavation & foundation | 60 hrs · crew of 3 (assumption) | $34.67–$59.19/hr | $2,080 – $3,552 |
| Foundation masonry | 44 hrs · crew of 2 (assumption) | $36.51–$50.86/hr | $1,607 – $2,238 |
| Framing & roof tie-in | 168 hrs · crew of 3 (assumption) | $31.02–$48.32/hr | $5,212 – $8,117 |
| Roofing | 36 hrs · crew of 2 (assumption) | $29.33–$40.28/hr | $1,056 – $1,450 |
| Electrical | 48 hrs · crew of 1 (assumption) | $31.92–$51.27/hr | $1,532 – $2,461 |
| Plumbing (if any) | 32 hrs · crew of 1 (assumption) | $31.88–$53.66/hr | $1,020 – $1,717 |
| HVAC extension | 36 hrs · crew of 2 (assumption) | $30.83–$49.8/hr | $1,110 – $1,793 |
| Insulation | 24 hrs · crew of 2 (assumption) | $29.11–$50.67/hr | $699 – $1,216 |
| Drywall | 60 hrs · crew of 2 (assumption) | $31.34–$45.19/hr | $1,880 – $2,711 |
| Flooring | 36 hrs · crew of 2 (assumption) | $31.53–$46.4/hr | $1,135 – $1,670 |
| Paint & finish | 36 hrs · crew of 1 (assumption) | $28.04–$39.36/hr | $1,009 – $1,417 |
Trades this project needs, in order
- Excavation & foundation
- Foundation masonry
- Framing & roof tie-in
- Roofing
- Electrical — licensed pro
- Plumbing (if any) — licensed pro
- HVAC extension — licensed pro
- Insulation
- Drywall
- Flooring
- Paint & finish