How much does a detached garage / pole barn cost?

For a typical 720 sq ft of building project at a mid finish level in the Jackson, Ohio area, the estimated range is $46,137 – $81,137.

Estimated range — not a quote. Your contractor's bid is the real number.

What drives the price

Materials (typical project — ranges)

MaterialQuantitySubtotal range
Concrete slab & foundation792 sq ft$8,336 – $10,609
Framing / pole barn package792 sq ft$12,183 – $15,505
Roofing package792 sq ft$7,053 – $8,977
Siding & exterior trim792 sq ft$6,412 – $8,161
Overhead door set1 sets$2,429 – $3,091
Electrical materials792 sq ft$4,488 – $5,713

Labor by trade (ranges & stated assumptions)

TradeHours & crewLocal labor cost rangeSubtotal range
Excavation & site prep43.2 hrs · crew of 2 (assumption)$34.67–$59.19/hr$1,498 – $2,557
Slab form, pour & finish64.8 hrs · crew of 3 (assumption)$31.32–$48.83/hr$2,029 – $3,164
Framing, siding & doors201.6 hrs · crew of 3 (assumption)$31.02–$48.32/hr$6,254 – $9,741
Roofing57.6 hrs · crew of 2 (assumption)$29.33–$40.28/hr$1,689 – $2,320
Electrical service & lighting43.2 hrs · crew of 1 (assumption)$31.92–$51.27/hr$1,379 – $2,215

Trades this project needs, in order

  1. Excavation & site prep
  2. Slab form, pour & finish
  3. Framing, siding & doors
  4. Roofing
  5. Electrical service & lighting — licensed pro

Get your own estimate

Your own estimate is free. Want it as a document you can plan and compare bids with? The Project Plan ($49 one-time) — scope breakdown, budget worksheet, bid-comparison kit, and red-flag guide, built from your project's numbers — is offered the moment your estimate is ready.