How much does a barndominium build cost?

For a typical 2000 sq ft of living area project at a mid finish level in the Jackson, Ohio area, the estimated range is $243,599 – $428,399.

Estimated range — not a quote. Your contractor's bid is the real number.

What drives the price

Materials (typical project — ranges)

MaterialQuantitySubtotal range
Concrete slab & foundation2200 sq ft$23,155 – $29,469
Steel shell & framing package2200 sq ft$35,622 – $45,338
Roofing package2200 sq ft$16,030 – $20,402
Insulation & drywall2200 sq ft$17,811 – $22,669
Windows & exterior doors16 openings$14,897 – $18,959
Kitchen & bath package allowance1 packages$22,669 – $28,851
Electrical, plumbing & HVAC materials2200 sq ft$35,622 – $45,338
Flooring & interior trim2200 sq ft$21,373 – $27,203
Paint materials2200 sq ft$4,453 – $5,667

Materials takeoff — what to order (typical project)

ItemWhat's in itNet quantityWaste allowanceOrder quantity
Concrete slab & foundation2000 sq ft5% (Concrete & masonry (bulk))2100 sq ft
Steel shell & framing packageManufactured steel shell package + interior framing lumber2000 sq ft10% (General materials)2200 sq ft
Roofing packageShingles or metal, underlayment, flashing & vents at the line quantity2000 sq ft10% (Roofing materials)2200 sq ft
Insulation & drywallInsulation batts + drywall — sheet count is 4×8 sheets at 32 sq ft coverage per sheet2000 sq ft10% (Sheet goods (drywall, panels, decking))2200 sq ft
69 sheets — drywall sheets (4×8)
Windows & exterior doorsWindow & exterior door units — count is the openings count16 openings0% (Fixtures, equipment & packages)16 openings
Kitchen & bath package allowanceCabinets, counters, fixtures & finishes for the kitchen and the baths — one package per project1 packages0% (Fixtures, equipment & packages)1 packages
Electrical, plumbing & HVAC materials2000 sq ft10% (General materials)2200 sq ft
Flooring & interior trim2000 sq ft10% (Flooring)2200 sq ft
Paint materialsPaint & primer — gallons figured from wall area at paint time2000 sq ft10% (General materials)2200 sq ft

Planning list only — it never changes the estimate price. Net is the quantity the job consumes; Order adds the waste allowance for the material class (the estimate breakdown quantities already include a flat 10% waste factor — this list re-derives net vs order by class, so nothing is counted twice). Counts (studs, sheets, bundles, rolls) use the standard planning conversions stated on each line; confirm counts against the actual plans before ordering.

Labor by trade (ranges & stated assumptions)

TradeHours & crewLocal labor cost rangeSubtotal range
Site work & excavation160 hrs · crew of 3 (assumption)$34.67–$59.19/hr$5,546 – $9,471
Slab form, pour & finish140 hrs · crew of 3 (assumption)$31.32–$48.83/hr$4,384 – $6,837
Shell erection & framing760 hrs · crew of 3 (assumption)$31.02–$48.32/hr$23,577 – $36,722
Roofing140 hrs · crew of 2 (assumption)$29.33–$40.28/hr$4,106 – $5,639
Electrical280 hrs · crew of 2 (assumption)$31.92–$51.27/hr$8,939 – $14,356
Plumbing280 hrs · crew of 2 (assumption)$31.88–$53.66/hr$8,926 – $15,026
HVAC200 hrs · crew of 2 (assumption)$30.83–$49.8/hr$6,166 – $9,960
Insulation120 hrs · crew of 2 (assumption)$29.11–$50.67/hr$3,493 – $6,081
Drywall hang & finish280 hrs · crew of 3 (assumption)$31.34–$45.19/hr$8,774 – $12,653
Flooring install180 hrs · crew of 2 (assumption)$31.53–$46.4/hr$5,675 – $8,351
Paint & finish180 hrs · crew of 1 (assumption)$28.04–$39.36/hr$5,047 – $7,084
General labor & cleanup200 hrs · crew of 3 (assumption)$29.27–$47.37/hr$5,853 – $9,474

Trades this project needs, in order

  1. Site work & excavation
  2. Slab form, pour & finish
  3. Shell erection & framing
  4. Roofing
  5. Electrical — licensed pro
  6. Plumbing — licensed pro
  7. HVAC — licensed pro
  8. Insulation
  9. Drywall hang & finish
  10. Flooring install
  11. Paint & finish
  12. General labor & cleanup

Get your own estimate

Your own estimate is free. Want it as a document you can plan and compare bids with? The Project Plan ($49 one-time) — scope breakdown, budget worksheet, bid-comparison kit, and red-flag guide, built from your project's numbers — is offered the moment your estimate is ready.